Liquefied Gas Carrier

Home page||| LNG handling ||| LPG handling||| Other Gas products||| Fire & Safety||| Emergency response |||

Onboard procedures for loading LNG cargo - gas carrier guide

LNG is liquefied natural gas, which is the very cold liquid form of natural gas.LNG carriers are generally specialised ships transporting LNG at its atmospheric pressure boiling point of approximately -162 degree C, depending on the cargo grade.LNG carriers were typically in the range 80-135,000 m3 up until 2006.



Before loading operations begin, the pre-operational ship/shore procedures must be thoroughly discussed and followed. Appropriate information exchange is required and the relevant parts of the ship/shore safety check list should be completed.

LNG bunkering

LNG loading

Line Cool Down

The terminal should be instructed to begin pumping at a slow rate for approximately 15 minutes, in order to gradually cool down the terminal piping and the ship’s headers. Slowly increase the terminal pumping rate until the liquid main and spray headers have cooled down (approximately 15/20 minutes). Cargo tank pressures should be monitored closely and if required the HD compressor should be adjusted in order to maintain a constant vapour pressure.

Note !
In order to avoid the possibility of pipe sections hogging, (contracting at the bottom more than at the top and thus causing flanges and long pipe sections to be stressed) the liquid header and crossovers must be cooled down and filled as quickly as possible.


LNG loading arms

Prior to commencing the loading operation the cargo pipelines have to be cooled. The primary reasons for cooling the cargo lines are:

i) To minimize the possibility of leaks being created at joints with valves or other sections of pipeline as they contract when cargo is passed.

ii) To reduce the possibility of sudden shock loadings on bellows as pipes contract rapidly.

iii) To avoid the formation of vapor locks in the pipelines when cargo is introduced. If LNG is introduced into a warm pipeline the initial cargo will vaporize, create a large pressure that can ‘block’ the loading of the liquid. It is then possible that this vapour will then condense very rapidly as the temperature reduces below the condensation point, allowing the liquid to surge along the pipeline possibly resulting in damage to the pipelines, valves or connections.

Air purge of loading arms

After the connection of loading arms, air should be purged from the loading arms and the tips of manifold pipes. N2 gas is lead into the loading arms from injection lines connected to the arms, and then pressurize up to about 4 to 6 kg/cm2G.

After pressurization, the ship’s liquid manifold vent valve and vapor manifold vent/drain valve are opened to release air and N2 gas into the atmosphere. While this operation is repeated two or three times, a leak test (with soap solution) is conducted at the same time. Air purge comes to an end when the oxygen content of the purged gas has dropped below 2%.


Loading Arms Cool Down

The cool down of the loading arms is performed from shore side by use of a small capacity pump. At a discharge port, the arms are cooled down by sending in LNG by ship’s spray pump.


Loading Operation

LNG is loaded via the loading manifolds to the liquid header and then to each tank filling line. The boil-off and displaced vapour leave each tank via the vapour suction to the vapour header. The vapour is initially free-flowed to shore via vapour crossover manifold and, as tank pressure rises, one compressor is brought into operation to increase the gas flow to shore and limit the vapour main and cargo tank pressure.

As the loading rate increases, it is important to monitor the tank pressures and to start one HD compressor. If the compressors are unable to cope with the volume of boil-off and displaced gas, it will be necessary to reduce the loading rate.


LNG carrier seaway

Fig:LNG bulk loading diagram


Bulk loading

When all lines and valves are fully cooled the vessel can commence ramping up the loading rate in the sequence agreed with the terminal. Deballasting should be commenced in accordance with the cargo plan. The cargo should be evenly distributed during the loading.

Ensure the HD compressors are adjusted in line with loading rate to ensure that the tank vapour pressure remains at a level safely below the lifting pressure of the relief valves. Ensure Nitrogen system is performing correctly.

Moss vessels will require the temperature gradient (with particular reference to the equator) to remain within certain limits, the tank temperatures are therefore to be closely monitored. Hourly temperatures are to be recorded in order that if required the vessel can verify that temperature has stayed within the manufacturers tolerances.

If not already started membrane ships should start appropriate cofferdam heating. Communications with the terminal should be tested on a frequent basis. Remote gauging devices and valve position indicators should be verified against local readouts at regular intervals during the operation. Moorings should be diligently attended and vessel movement with respect to loading arms closely monitored, if required additional persons are to be called to assist with the moorings. If at any time the OOW is in doubt a senior officer or the Master should be called.


Topping off

As the vessel approaches completion of cargo operations the tanks should be staggered in line with the cargo plan, typically this would leave a gap of 10 to 15 minutes between completion of each tank. The terminal is to be notified well in advance and in line with the agreed procedure that the vessel is topping of and will need to reduce loading rate. Notification should be made at least 30 minutes before reducing rate.

Note: Membrane tanks normally fill to 98% where as Moss vessels normally fill to 99.5%. On all vessels the independent alarms activate at preset filling levels, the upper alarm activates the ESD if previous alarms are ignored.


Deballasting

The deballasting operation is carried out simultaneously with the cargo loading operation. Before any de-ballasting commences, all ballast surfaces should be visually checked and confirmed as free from oil or other pollutants. This check must be carried out through inspection hatches / tank lids. This is particularly important for ballast tanks which are situated adjacent to fuel oil tanks. If fitted, gas detection / sampling systems may not indicate the presence of hydrocarbons particularly in small quantities.

Deballasting is initially carried out by gravity discharge until the level in the ballast tanks approach the vessels water line when the ballast pumps are used.

The ballast should be adjusted to keep a small stern trim to aid with the stripping of the ballast tanks. The flow rate of the ballast should be adjusted to keep the ship within 1 meter of the arrival draft or as specified by the terminal. Deballasting should normally be completed before the start of the topping off of the cargo tanks.


Filling Rate of Cargo Tanks

The IGC Code (International Code for the Construction and Equipment of Ships Carrying Liquefied Gases in Bulk) came into force on July 1, 1986, in accordance with the International Convention on the Safety of Life at Sea, 1983 (the 1974 SOLAS Convention, as amended in 1983), and, following this, the Regulations Relating to the Carriage and Storage of Dangerous Goods by Ship was revised in Japan. The IGC Code contains a chapter for “Filling Limits for Cargo Tanks”.

LNG carriers registered in Japan are NK-class ships and constructed on the basis of NK’s “Rules and Guidance for the Survey and Construction of Steel Ships – Part N”. These rules reflect the IGC Code, as it is, and, as a result, our LNG carriers, though built before the enforcement of the ’83 SOLAS Convention, meet requirements for new ships in the IGC Code.


Behaviour of LNG in the cargo tanks

When loaded in the cargo tanks, the pressure of the vapour phase is maintained substantially constant, slightly above atmospheric pressure.

The external heat passing through the tank insulation generates convection currents within the bulk cargo, causing heated LNG to rise to the surface where it vaporizes. The heat necessary for vaporization comes from the LNG, and as long as the vapour is continuously removed by maintaining the pressure as substantially constant, the LNG remains at its boiling temperature.

If the vapour pressure is reduced by removing more vapour that is generated, the LNG temperature will decrease. In order to make up the equilibrium pressure corresponding to its temperature, the vaporization of LNG is accelerated, resulting in an increase heat transfer from LNG to vapour.

If the vapour pressure is increased by removing less vapour than is generated, the LNG temperature will increase. In order to reduce the pressure to a level corresponding to the equilibrium with its temperature, the vaporization of LNG is slowed down and the heat transfer from LNG to vapour is reduced.

LNG is a mixture of several components with different physical properties, particularly the vaporization rates; the more volatile fraction of the cargo vaporizes at a greater rate that the less volatile fraction. The vapour generated by the boiling of the cargo contains a higher concentration of the more volatile fraction than the LNG.




The properties of the LNG, i.e. the boiling point, density and heating value, have a tendency to increase during the voyage.

Typical LNG vessel at loading terminal

Fig:Typical LNG vessel at loading terminal

Below is our additional guideline for handling LNG cargo:

Preparation for loading LNG cargo

Drying of Cargo Tanks and preparation for loading LNG cargo

Inerting of Cargo Tanks prior loading LNG cargo

Gassing-up requirement for cargo tanks

Initial Cool Down of cargo tanks

LNG spill risk during marine transportation and hazards associated

Toxicity and associated health hazards in liquefied Gas Carrier

Safety check items prior loading LNG cargo

Procedures for LNG cargo discharging

Use of cargo as fuel -Boil-off from LNG cargo burnt as fuel in the main propulsion system

Details of various cargo handling equipment onboard



Related Information:

  1. Liquefied gas carrier safety training


  2. Increased Cargo Capacity for LNG ships & Advantages of the dual fuel diesel electric propulsion


LNG ship spillage risk

LNG shipment

Leaks on the Cargo System, Continuous Flow - how to prevent

LNG tank leaks and immediate action by gas carriers

Leaks from a Loading Arm due to Tidal or Current Effects

Minor or major leaks from LNG tanks

Risk of Overfilling of Cargo Tank during Loading



External links :

  1. Cryogenic Fuels Inc. - Provides reliable, cost effective fully integrated LNG (liquefied natural gas) vehicular fuel systems






// Home page/// LNG handling /// LPG handling/// Sea transport /// Gas products///

Cargo work ///Fire precautions ///Health hazards ///Safety Precautions

///Emergency response ///




Copyright © Liquefied Gas Carrie.com All rights reserved.


The content published in this website are for general reference only. We have endeavoured to make the information as accurate as possible but cannot take responsibility for any errors. For latest information please visit www.imo.org . Any suggestions, please Contact us !

///Links &Resources // Terms of use/// Privacy policy///Home page///