Liquefied Gas Carrier

Home page||| LNG handling ||| LPG handling||| Other Gas products||| Fire & Safety||| Emergency response |||

Cargo tank inerting prior to gassing up - LPG tanker procedure

LPG cargo tanks - why inerting ?

Inerting cargo tanks and pipework systems is undertaken primarily to ensure a non-flammable condition in the subsequent gassing up with the vapour of the cargo to be loaded. For this purpose a reduction in the oxygen concentration to 5% by volume is generally judged to be adequate, although lower values are usually obtainable and preferred.

For some of the more active chemical gases, VCM or butadiene, oxygen levels as low as 0.1% may be required to avoid chemical reaction with the incoming gassing-up vapour. This level will be difficult to achieve using shipboard inert gas plant.



Inerting by displacement

This is generally considered to be the most efficient method of inerting tanks. It relies on stratification in the tank as a result of the difference in vapour densities between the gas entering the tanks and the gas already in the tank. The heavier gas is introduced beneath the lighter gas, and at a low velocity to minimise turbulence. If perfect stratification could be achieved with no mixing at the interface, then one tank volume of the inert gas would completely displace the gas already in the tank.

In practice some mixing does occur and it will be necessary to use more than one tank volume of inert gas. This may vary from 1.25 to 4 times the tank volume, depending upon the relative densities and tank and piping configurations. There is little density difference between air and inert gas; inert gas from a combustion generator is slightly heavier than air while nitrogen is slightly lighter. These small density differences make inerting by displacement alone very difficult to achieve, and usually the process becomes partly displacement, partly dilution.

Before introducing nitrogen a purge with dry air is usual. The relative densities of nitrogen and air are similar which makes the change over from air to nitrogen, and the clearance of all air from the tank difficult. In order to improve the separation during this process the dry air in the tank should be as cold as possible, and the nitrogen as warm as possible.

The nitrogen must be introduced through the upper distribution line with displacement taking place in the direction top to bottom.

This process must not be hurried. Nitrogen gas is expensive, and the need to re-inert following an unsuccessful first attempt is costly and time consuming.

Tanks can be inerted in parallel or series, and with flow within the tanks or either top to bottom or bottom to top, depending on the relative densities of the two gases.


Inerting by dilution

In the dilution method the incoming gas mixes with the vapour already in the tank. This can be done in several ways depending on the type of the vessel:


Repeated pressurisation (not on fully refrigerated vessels)

Dilution can be achieved by a process of repeated pressurisation of the tank with inert gas using a compressor, followed by a release of the compressed contents to atmosphere. Each repetition will bring the tank contents nearer to the oxygen concentration level of the injected inert gas. Thus to bring the tank contents to a level of 5% oxygen within a reasonable number of repetitions, an inert gas quality better than 5% oxygen content is required.

Quicker results will be achieved by more numerous repetitions each at a lower pressurisation level, than by fewer repetitions using the higher pressurisation levels, of which the tank and compressor may be capable.


Repeated vacuum (not on fully refrigerated vessels)

Inerting by successive dilutions may be carried out by repeatedly drawing a vacuum on the tank by the compressors, and then breaking the vacuum using inert gas. If, for instance a 50% vacuum can be drawn then on each vacuum cycle half the oxygen content of the tank will be withdrawn.

Some of the withdrawn oxygen will, of course, be replaced by the oxygen content of the subsequent vacuum breaking inert gas but, if the quality of inert gas is good, this method is probably the most economical in the use of minimum inert gas quantity in order to achieve the desired inerting level in the tank. The overall time taken may be longer than with pressurisation because of the reduction in capacity of the compressor on vacuum, and the limitation of the rate of vacuum breaking output capacity of the inert gas generator.


Continuous dilution

Inerting by dilution can be a continuous process. An increased flow of inert gas and hence better mixing and a reduction in overall time may be achieved by maintaining the tank under vacuum by passing the diluted efflux through the compressor. Care must be taken to ensure continued good quality inert gas under the increased outflow conditions of the inert gas generator.

It is immaterial where the inert gas inlet or the tank outlet is located provided that good mixing is achieved. It is generally found more satisfactory to introduce the inert gas at high speed through the vapour line and exit through the liquid loading line. Where several tanks are to be inerted it may be possible to achieve a reduction in the total quantity of inert gas used, and in the overall time, but inerting two or more tanks in series. This procedure also provides a ready way of inerting pipework and equipment at the same time.


Ammonia

Inert gas from a combustion type generator must never be used in preparation for carrying ammonia because of the reaction of ammonia vapour with the carbon dioxide content of such inert gas to form carbamates.

Normally, however, inerting prior to loading ammonia is not required because it is recognised that ammonia vapour, though flammable, is not readily ignited. Liquid ammonia must never be sprayed into a tank containing air as there is a risk of creating a static charge which would cause ignition, and the conditions for ammonia stress corrosion cracking. If the ship's Flag Administration or the loading terminal require inerting prior to loading ammonia then nitrogen should be used.


Compressors and reliquefaction

If the compressors are used to create vacuum in the tanks, they are to be connected on the suction side to the tank gas suction lines on deck, and on the discharge side to the gas discharge lines on deck.

If condensable gas is drawn from the tanks this may be reliquefied and discharged ashore via the condensate and liquid cross over lines, or to the deck tank or another cargo tank.

When using the compressors care must be taken to avoid raising the level of non-condensable gases (nitrogen/inert gas) thus causing an increase in the temperature and pressure in the condenser, and overheating at the compressor outlet as this will stop the reliquefaction process.




Preparation for gassing up and cooling down

If possible a quantity of the next, or compatible, cargo should be taken into a deck tank for the voyage to the loading port. This will enable the gassing up and cooling down process to be started during the ballast passage. The limited quantity of cargo may mean that only one or two tanks can be prepared, but this would be a useful contribution to minimising port time.



Related Information:

  1. LPG cargo loading special guideline


  2. Tackling fire onboard LNG & LPG ships


  3. Detail guideline for Ballast operation at sea by LPG carrier


  4. Handling cargo related documents for LPG carrier


  5. Cargo sampling procedure for liquefied gas cargo


  6. Cargo measurement and calculation guideline for LPG carriers


  7. Handling Propylene oxide, Ethylene oxide mixtures


  8. Special characteristics of Vinyl Chloride Monomer & Butadiene








// Home page/// LNG handling /// LPG handling/// Sea transport /// Gas products///

Cargo work ///Fire precautions ///Health hazards ///Safety Precautions

///Emergency response ///




Copyright © Liquefied Gas Carrier.com All rights reserved.


The content published in this website are for general reference only. We have endeavoured to make the information as accurate as possible but cannot take responsibility for any errors. For latest information please visit www.imo.org . Any suggestions, please Contact us !

///Links &Resources // Terms of use/// Privacy policy///Home page///