Home page|||
LNG handling |||
LPG handling||| Other Gas products|||
Fire & Safety|||
Emergency response |||
Discharging LPG - Safety & operational procedures
Preparations for LPG discharging
When the vessel arrives at the discharge terminal, cargo tank pressures and temperatures must be at
values appropriate to the terminal requirements to allow maximum discharge rates to be achieved.
Before the discharge operation begins, the pre-operational ship/shore procedures must be carried out,
i.e. ship/shore information exchange, ship/shore safety check list.
The following information will be required to set the principle discharge plant parameters:
- Which side is the ship to berth?
- Will there be a vapour return line?
- What size is the vapour and discharge lines?
- What are the normal and maximum permitted back pressures?
- Required temperature of the cargo.
- Slow down, speed up and emergency procedures.
NOTE: THE COMPANY AND CHARTERER ARE ALWAYS TO BE ADVISED PRIOR TO USING A
SHORE VAPOUR RETURN AS THIS MAY HAVE IMPORTANT IMPLICATIONS AFFECTING THE
CHARTER PARTY OR OTHER COMMERCIAL CONSIDERATIONS.
Three basic methods may be used to discharge cargo:
- Vapour pressure.
- Cargo pumps with our without boosters.
- Cargo pumps through a cargo heater and a booster pump.
Discharge by vapour pressure is unlikely to be used.
All unused manifolds are to be blanked.
When discharging using the cargo pumps running in parallel, it should be noted that trying to increase
the rate of discharge by running all the pumps may not result in the expected increase due to
constraints in the overall system. Also, the increased energy imparted to the cargo is dissipated as
heat and results in an increase in liquid temperature, which in turn increases the flash gas produced
when the cargo discharges into the shore terminal. This may cause the terminal to ask for a reduction
in the flow.
Observing the manifold pressure gauges will provide a good indication of whether or not the correct
number of pumps is being used. The discharge rate must not be reduced by throttling the valves at
the crossover if the shore cannot accept the discharge rate. This will only heat up the cargo. The
principle method of flow control is by throttling the booster pump discharge or the main pump
circulation or by a combination of the two. Control of flow solely by throttling the main pump discharge
may cause loss of booster pump suction.
The required NPSH (Net Positive Suction Head) valve of the cargo pumps is relatively low due to the
fitted inducer, and it is possible to unload down to a level of approximately 65cm. For further
unloading, the capacity of the pumps must be throttled or the pressure of the gas pad above the liquid
increased, otherwise the tank pressure can fall below atmospheric pressure causing the pump to stop.
Replacement of the unloaded liquid in the tank by additional gas is normally not necessary, except for a
cargo under atmospheric pressure, and this only at the end of the discharge.
Where cargo is being transferred into pressurised storage, it will almost certainly be necessary to warm
the cargo on discharge.
Cargo pumps
Deep well and booster pumps are fitted with differential pressure switches which shut down the pumps
if the pressure difference across the pumps and/or the outflow falls below set limits.
The maximum capacity when all deep well pumps are running is a rated figure which is unlikely to be
achieved throughout a total discharge when pumping against shore pressure.
The upper pressure limit switch is set to approximately 22 barg and when this is reached, the quick
closing valves on the cross over line will close, initiating the shutting down of both deep well and
booster pumps. Therefore, it is necessary to set the maximum operating pressure to below 22 barg,
using the pressure controllers between the pump suctions and discharged.
When running two deep well pumps in conjunction with a booster pump, the hand controlled discharge
valve must not be throttled because this may have a detrimental effect on the suction pressure of the
booster pump. Instead, the discharge valves on the deep well pumps are to be used to control the
discharge from the two tank compartments.
To avoid cavitation or gassing-up of a pump when handling boiling liquids, the pressure at the pump
suction must exceed the saturated vapour pressure (SVP) of the liquid by an amount termed the Net
Positive Suction Head (NPSH). The required minimum NPSH, expressed as an equivalent head of liquid
above the pump suction, may vary from 1 metre at maximum pump capacity to 200mm at practical
reduced flow. If the vapour space pressure can be increased above the SVP by the supply of extra
vapour from shore vapour return or shipboard vaporiser, the onset of cavitation as the liquid level
approaches the bottom of the tank can be delayed. This procedure is most frequently used where
maximum possible cargo outturn is required prior to gas freeing.
Before starting booster pumps, ensure that the combined pressure produced by the main plus booster
pumps will not exceed the maximum system operating pressure, otherwise the pumps will be stopped
automatically and the relief valves may lift.
VCM must not be unloaded with deep well and booster pumps running in series, because
the high density of VCM may cause overpressure. The booster pumps on their own can be
used to discharge VCM in emergency conditions.
DISCHARGING CARGO
Prior to commencing the discharge, all preparatory liaison with terminal staff is to have been
completed, including communications systems, safety and emergency procedures, inspections and
preparation of an agreed discharge plan. After the manifold valves are opened, the first pump should
be started discharging back to the tank. When it is running satisfactorily the discharge valve can be
opened slowly and the cargo discharged ashore. The other pumps can then be started in sequence.
If booster pumps are used to increase the discharge pressure they must be primed from a
deep well pump. Booster pumps can be used to discharge at low rates of flow.
CARGO HEATING DURING THE DISCHARGE
When cargo is being transferred into pressurised storage, it may be necessary to warm the cargo on
discharge; this means running the cargo booster pump and cargo heater in series with the main cargo
pump. To operate the booster pump and heater, it is necessary to first establish the correct sea water
flow through the heater.
Thereafter, to avoid thermal shocks, the pump and heater may be slowly cooled down prior to
operation by carefully bleeding in liquid from the main cargo pump discharge. Once cooled down, the
discharge valve can be opened until the desired outlet temperature is reached.
It is important to ensure that the main cargo pumps maintain adequate suction to the
booster pump at all times
Cargo heating always carries with it the risk of freezing the heater circulating water. As well as
checking the cargo outlet temperature and the booster pump suction during operation, attention is to
be paid to the sea water inlet and outlet temperatures and pressure.
A minimum sea water temperature of +10 degree C is normally required to provide satisfactory cargo heating.
In the case of a lower temperature, it may be possible to achieve satisfactory heating by slowing the
rate of discharge, but under these circumstances great care will be required if freezing of water in the
heater tubes is to be prevented.
The heat exchanger is protected by a temperature switch which stops the flow of cargo if
the sea water drops below +5 degree C.
Water for the heater is supplied by the condenser cooling water system.
The main danger with cargo heating is water freezing in the heat exchanger tubes. This
can be prevented by maintaining a high rate of sea water flow through the tubes.
The minimum discharge temperature of the cargo is set by the transmitter controller and limiting valve.
Control of the cargo temperature above the minimum temperature is made by controlling the flow
through the heater by pass line.
For cargoes with an inlet temperature at the heater warmer than -15 degree C, the sea water
temperature must not be less than +5 degree C; for cargoes with a temperature colder than -15 degree C
the sea water temperature is not to be less than +10 degree C.
On completion of cargo heating, the heater is to be drained back to a cargo tank. When it is confirmed
that all liquid has totally evaporated the flow of seawater can be stopped.
CARGO TANK STRIPPING
NORMAL STRIPPING
The following procedures are used when the loading of a compatible cargo follows the discharge.
With the deep well pumps running at full capacity, the tank can be emptied down to approximately
65cm from the bottom of the discharge well. At this level, the discharge is to be throttled at the
discharge control valve, to maintain suction. Pressure above the liquid may be increased by shore
supplied vapour or by using the compressors. When using compressors vapour can be drawn from an
already discharged tank, or from the vaporiser.
When using this method to strip a tank containing VCM the pressure difference between
the two tanks should be 2.5 bar, 1.5 bar when stripping propane and 1.7 bar for ammonia.
For a short time during the early stages of stripping, the compressed vapour will condense on the cold
tank walls and tend to inhibit the stripping process, but as the tank walls begin to warm condensation
stops and stripping proceeds.
A calculated minimum quantity of liquid is to remain in the tanks to keep the tanks cold during the
ballast passage.
On completion of the cargo discharge and stripping, liquid must be drained from all deck lines, cargo
hoses or hard arms. This can be done either from ship to shore using a cargo compressor, or from
shore to ship, normally by blowing the liquid into the ship's tanks using nitrogen injected at the base of
the hard area. Only after depressurising all deck lines is the ship/shore connection to be broken.
If, during this operation, liquid quantities in excess of the designed amount flow to the mast, a level
switch will shut down the plant and close all hydraulic valves. The cause of this excessive flow must be
investigated before attempting to re-start the plant.
STRIPPING FOR COMPLETE DISCHARGE
Stripping for complete discharge is required prior to changing between incompatible cargoes, when gas
freeing and when specific instructions are given to avoid any mixing of previous and new cargoes.
It is important not to under-estimate the quantity of vapour remaining in the tanks after
total unloading of all liquid.
The tanks are to have pressure restored to above the SVP before the cargo pumps start to drain the
tanks to delay the onset of pump cavitation. Pressure above the liquid is to be increased by
introducing vapour from the vapour return line or by running the compressors. Vapour can also be
drawn from an already emptied tank or from the vaporiser.
When using this method to strip a tank containing VCM the pressure difference between
the two tanks should be 2.5 bar, 1.5 bar when stripping propane and 1.7 bar for ammonia.
For a short time during the early stages of stripping, the compressed vapour will condense on the cold
tank walls and tend to inhibit the stripping process, but as the tank walls begin to warm condensation
stops and stripping proceeds. Final clearance of liquid will be accomplished by vaporising the
remainders - this will also help to warm the tank walls.
Vapour is drawn from the tank, heated in the superheater section of the vaporiser and returned to the
tank sump through the stripping line or the bottom distribution line. The warm vapour jet sprays onto
the liquid collected in the sump which quickly vaporises. An increase in the temperature of the tank
sump signals the completion of vaporisation.
THIS PROCEDURE MUST NOT BE HURRIED. During boiling off it is important to obtain a
positive temperature reading on the sump thermometer. Any subsequent drop in
temperature indicates that liquid may still be present hence it is important to monitor the
temperature even after the flow of hot gas has stopped.
If there is insufficient cargo in the system to support this closed cycle operation, this will result in low
pressure, and in this case a quantity of liquid cargo from ashore or the deck tank is to be vaporised and
injected into the circuit. Inert gas or nitrogen can also be used to accelerate this procedure, but it
must be remembered that the total contents of the tank, (nitrogen/inert gas and cargo vapour mix) will
be lost.
When all liquid has finally been cleared from the tank the vapour sucked on by the compressors can be
condensed and unloaded to shore or the deck tank.
On completion of the cargo discharge and stripping liquid must be drained from all deck lines, cargo
hoses or hard arms. This is usually done from ship to shore using a cargo compressor. Only after
depressurising all deck lines is the ship/shore connection to be broken.
Liquid quantities in excess of the designed amount flowing to the mast will cause a level
switch to stop all machines and close all hydraulic valves. To restart the system, the
drainings are to be drained to atmosphere via the bottom valve and a flexible hose, and
allowed to evaporate or hosed with water.
One of the following procedures will follow the unloading:
- Loading of the same or compatible cargo
- Purging and/or gas freeing for an incompatible cargo, tank inspection or dry docking. (Tanks
must be totally unloaded, vapour from tanks liquefied and unloaded to shore or deck tank).
- Ballast voyage. (A quantity of cargo should remain in the tanks to maintain tank temperature).
Ice in suspension
With some cargoes ice can be held in suspension, and some ice can remain in the tank atmosphere
after the discharge. This will cause little or no problem providing the tank temperature is maintained
below 0 degree C on the ballast voyage.
Serious problems can occur if the tank temperature is allowed to rise above freezing point - ice held in
suspension will melt and collect in the sump, this water will then refreeze in the sump when cooled
below zero. This may cause problems with the gauging system.
Methanol can be injected into the pump discharge tube but this is not always completely successful.
If the tanks are allowed to warm-up above 0 degree C the sump sampling line is to be used to drain off any
accumulated water.
Related Information:
- Various type LPG tanker - Design characteristics and usability
- Preparations for loading compatible cargo onboard LPG tanker
- Preparation for changing different grade cargo or drydocking -LPG tanker guideline
- Cargo tank inerting prior to gassing up - LPG tanker procedure
- LPG cargo tank purging & safety guideline
- LPG cargo tank cooling safety procedure
- LPG cargo loading special guideline
- Tackling fire onboard LNG & LPG ships
- Detail guideline for Ballast operation at sea by LPG carrier
- Handling cargo related documents for LPG carrier
- Cargo sampling procedure for liquefied gas cargo
- Cargo measurement and calculation guideline for LPG carriers
- Handling Propylene oxide, Ethylene oxide mixtures
- Special characteristics of Vinyl Chloride Monomer & Butadiene
- Various type LPG tanker - Design characteristics and usability
- LPG tanker cargo work equipments & product line system
- Carriage of LPG cargo at sea & safety guideline
- LPG reliquefaction plant safety guideline
- Preparations for LPG cargo discharging, pumping & stripping guideline
- Preparations for loading compatible cargo onboard LPG tanker
- Preparation for changing different grade cargo or drydocking -LPG tanker guideline
- Cargo tank inerting prior to gassing up - LPG tanker procedure
- LPG cargo tank purging & safety guideline
- LPG cargo tank cooling safety procedure
- LPG cargo loading special guideline
- Tackling fire onboard LNG & LPG ships
- Detail guideline for Ballast operation at sea by LPG carrier
- Handling cargo related documents for LPG carrier
- Cargo sampling procedure for liquefied gas cargo
- Cargo measurement and calculation guideline for LPG carriers
- Handling Propylene oxide, Ethylene oxide mixtures
- Special characteristics of Vinyl Chloride Monomer & Butadiene
// Home page///
LNG handling ///
LPG handling///
Sea transport ///
Gas products///
Cargo work
///Fire precautions
///Health hazards
///Safety Precautions
///Emergency response ///
Copyright © Liquefied Gas Carrier.com All rights reserved.
The content published in this website are for general reference only. We have endeavoured to make the information
as accurate as possible but cannot take responsibility for any errors. For latest information please visit www.imo.org .
Any suggestions, please Contact us !
///Links &Resources //
Terms of use///
Privacy policy///Home page///